Response Time and Project Completion Time of Healthcare Sector Projects in Uasin Gishu County, Kenya

Authors

  • Sammy Kipkorir Kibiy Jomo Kenyatta University of Agriculture and Technology
  • Dr. Daniel M. Wanyoike Jomo Kenyatta University of Agriculture and Technology

DOI:

https://doi.org/10.47604/ijepm.4041

Keywords:

Response Time, Project Completion Time, Healthcare Projects, Project Delays, Uasin Gishu County

Abstract

Purpose: Delayed completion of healthcare projects limits the ability of hospitals to meet population demand. This study determined the influence of response time on project completion time of healthcare sector projects in Uasin Gishu County, Kenya.

Methodology: The study used a correlational research design. A census of all 152 personnel involved in managing healthcare projects in public hospitals in the county was carried out, and 114 (75%) returned completed questionnaires. Data collection was carried out using a structured five-point Likert scale questionnaire, which was pre-tested and proved reliable (Cronbach's alpha for the response time was 0.76 and for project completion time 0.70). Data were analysed using descriptive statistics, Pearson's correlation and simple linear regression in SPSS version 26.

Findings: Respondents rated response time as moderately effective (mean = 3.34, SD = 0.74), while project completion time received a moderate rating (mean = 3.08, SD = 0.68). Prompt detection of project problems recorded the lowest mean score (mean = 3.01), suggesting that early identification of project-related challenges requires improvement. Correlation analysis established a moderate positive and statistically significant relationship between response time and project completion time (r = 0.48, p < .001). Similarly, regression analysis revealed that response time had a positive and statistically significant effect on project completion time (β = 0.48, t = 5.79, p < .001). The regression model explained approximately 23% of the variation in project completion time (R² = 0.23), indicating that response time was an important predictor, although other factors accounted for the remaining variation. Consequently, the null hypothesis was rejected, demonstrating that response time had a statistically significant effect on project completion time.

Unique Contribution to Theory, Practice and Policy: The results support systems theory and contingency theory, since earlier detection and faster resolution of problems were associated with better schedule performance. Project teams should strengthen early problem detection and establish response routines that escalate problems within specified time frames, while the County Government should set response-time standards and include them in the monitoring and evaluation of healthcare projects.

Downloads

Download data is not yet available.

References

Bujang, M. A., Omar, E. D., & Baharum, N. A. (2018). A review on sample size determination for Cronbach’s alpha test: a simple guide for researchers. The Malaysian Journal of Medical Sciences, 25(6), 85. https://doi.org/10.21315/mjms2018.25.6.9

County Government of Uasin Gishu. (2024). Uasin Gishu County annual development plan (ADP) 2024/2025. https://uasingishu.go.ke/index.php/download/annual-development-plan-fy-2024-2025

Drack, M., & Pouvreau, D. (2015). On the history of Ludwig von Bertalanffy’s “General Systemology”, and on its relationship to cybernetics–part III: convergences and divergences. International Journal of General Systems, 44(5), 523-571. https://doi.org/10.1080/03081079.2014.1000642

Espinoza, R., & Presbitero, A. F. (2022). Delays in public investment projects. International Economics, 172, 297-310. https://doi.org/10.1016/j.inteco.2021.10.002

Fiedler, F. E. (1964). A contingency model of leadership effectiveness. In Advances in Experimental Social Psychology (Vol. 1, pp. 149-190). Academic Press. https://doi.org/10.1016/S0065-2601(08)60051-9

Harake, M. F. (2025). Strategic project management in crisis response: A comprehensive analysis of rescue agencies’ operations during emergencies. PM World Journal, 14(3). https://pmworldlibrary.net/wp-content/uploads/2025/03/pmwj150-Mar2025-Harake-Strategic-Project-Management-in-Crisis-Response.pdf

Harit, M., & Judson, L. (2023). Mitigation strategies for delay factors in healthcare projects. Journal of Building Construction, 5(1). https://doi.org/10.5281/zenodo.7615101

In, J. (2017). Introduction of a pilot study. Korean Journal of Anesthesiology, 70(6), 601–606. https://doi.org/10.4097/kjae.2017.70.6.601

Jamieson Gilmore, K., Bonciani, M., & Vainieri, M. (2022). A comparison of census and cohort sampling models for the longitudinal collection of user-reported data in the maternity care pathway: Mixed methods study. JMIR Medical Informatics, 10(3), e25477. https://doi.org/10.2196/25477

Karunakaran, P. (2020). The framework of direct and indirect effect of project risk response-related measures on project performance in managing construction delay (Doctoral dissertation, Universiti Tun Hussein Onn Malaysia). http://eprints.uthm.edu.my/id/eprint/941

Kerzner, H. (2003). Project management: A systems approach to planning, scheduling, and controlling (8th ed.). John Wiley & Sons.

Kolongei, L. (2025). Ziwa level five hospital stalls a decade on despite Sh1.4 billion investment. The Standard. https://www.standardmedia.co.ke/business/health-science/article/2001519550/ziwa-level-five-hospital-stalls-a-decade-on-despite-sh14-billion-investment

Kusongwa, R., Ngalesoni, O., & Kiende, H. (2025). Critical Factors Affecting Construction Project Cost and Schedule Adherence in Sub-Saharan Africa: A Systematic Review. Management and Social Perspectives, 4(1), 81-106. https://revue.univ-oran2.dz/Revue/MASP/index.php/MASP/article/view/8/7

Malematja, D. N., Nkosi, E. M., & Nene, S. E. (2025). The impact of insufficient resources on the quality-of-service delivery at a primary healthcare clinic in Limpopo. Curationis, 48(1), 2696. https://doi.org/10.4102/curationis.v48i1.2696

Melby, L., & Håland, E. (2021). When time matters: a qualitative study on hospital staff’s strategies for meeting the target times in cancer patient pathways. BMC Health Services Research, 21(1), 210. https://doi.org/10.1186/s12913-021-06224-7

Mittal, Y. K., Paul, V. K., Rostami, A., Riley, M., & Sawhney, A. (2020). Delay factors in construction of healthcare infrastructure projects: a comparison amongst developing countries. Asian Journal of Civil Engineering, 21(4), 649-661. https://doi.org/10.1007/s42107-020-00227-1

Mugenda, O. M., & Mugenda, A. G. (2003). Research methods: Quantitative & qualitative approaches. Acts Press.

Nyamamba, E. N., & Omwenga, J. (2022). Determinants of timely completion of construction projects in selected construction investment companies in Nairobi County. International Journal of Social Science and Humanities Research. https://doi.org/10.5281/zenodo.6567134

Ochola, G. M., & Malenya, A. (2020). Influence of project management practices on timely completion of education projects funded by Bondo National Government Constituency Development Fund, Siaya County, Kenya. The Strategic Journal of Business & Change Management, 7(2), 1-19.

Ranganathan, P., & Caduff, C. (2023). Designing and validating a research questionnaire-Part 1. Perspectives in Clinical Research, 14(3), 152–155. https://doi.org/10.4103/picr.picr_140_23

Rasul, N., Malik, M. S. A., Bakhtawar, B., & Thaheem, M. J. (2021). Risk assessment of fast-track projects: a systems-based approach. International Journal of Construction Management, 21(11), 1099-1114. https://doi.org/10.1080/15623599.2019.1602587

Seboru, M. (2015). An investigation into factors causing delays in road construction projects in Kenya. American Journal of Civil Engineering. https://doi.org/10.11648/j.ajce.20150303.11

Shah, S., Jepsen, D. M., & Bankins, S. (2022). It’s About Time: A Systematic Review of the Study of Time in Project Management. In Academy of Management Proceedings (Vol. 2022, No. 1, p. 15545). Academy of Management. https://doi.org/10.5465/AMBPP.2022.15545abstract

Tavakol, M., & Dennick, R. (2011). Making sense of Cronbach's alpha. International Journal of Medical Education, 2, 53. https://pmc.ncbi.nlm.nih.gov/articles/PMC4205511/

The Star. (2025). CS Duale commits Sh. 100m to revive stalled Ziwa Level 4 hospital project. https://www.the-star.co.ke/news/2025-09-10-cs-duale-commits-sh100m-to-revive-stalled-ziwa-level-4-hospital-project

Wanzala, D. T., Kibuine, M. K., & Akwalu, E. K. (2025). Influence of stakeholder engagement on completion of funded healthcare projects in Kenya. African Multidisciplinary Journal of Research, 2(3), 341-362. https://doi.org/10.71064/spu.amjr.2.3.2025.469

Wepari, J. W., Donkor, M. B., & Kusi, E. (2024). Mitigating the effects of delay risk in building construction projects in Ghana. Cogent Engineering, 11(1), 2345522. https://doi.org/10.1080/23311916.2024.2345522

Downloads

Published

2026-11-18

How to Cite

Kibiy, S., & Wanyoike, D. (2026). Response Time and Project Completion Time of Healthcare Sector Projects in Uasin Gishu County, Kenya. International Journal of Entrepreneurship and Project Management, 11(2), 1–11. https://doi.org/10.47604/ijepm.4041

Issue

Section

Articles

Similar Articles

1 2 3 4 5 6 > >> 