Influence of Project Initiation on Completion of United Nations Joint Programme on Local Governance Road Rehabilitation Projects

Authors

  • Karuri Solomon Waiganjo University of Nairobi
  • Ann Wangui Karanja University of Nairobi

DOI:

https://doi.org/10.47604/ijepm.1661

Keywords:

Project Initiation, Completion, United Nations Joint Programme, Local Governance Road Rehabilitation Projects

Abstract

Purpose: The purpose of this study was to examine the influence of project initiation on completion of United Nations Joint Programme on Local Governance road rehabilitation projects.

Methodology: This research study adopted a descriptive cross-sectional survey design. The target population was 250 staff working at UNJPLG road rehabilitation projects. The study population included project engineers, clerk of works, project managers, contractors, supervisors, community leaders, and donors making total of 250 respondents. The research study embraced stratified random sampling method and a sample size of 154 respondents was obtained using the Yamane (1967) formula. The study further used structured questionnaires which consisted of both open-ended and closed-ended questions to collect data from the selected respondents. A pilot study was also conducted to test the validity and reliability of the questionnaires. After data was collected, it was examined for efficiency, clarity and clearness. Coding was done on the basis of the place of the participants. Measurable information was evaluated utilizing Statistical Package for Social Sciences (SPSS Version 21) for Microsoft home windows that included detailed and inferential analysis. Data was presented using chart, frequency tables and pie charts.

Findings: The study established that project initiation had a significant influence on completion of road rehabilitation projects by United Nations Joint Programme on Local Governance. Findings indicate that the benefits of the road rehabilitation projects are effectively provided by United Nations Joint Programme on Local Governance which enhances their completion. Moreover, the purpose and objectives of road rehabilitation projects are well outlined by United Nations Joint Programme on Local Governance which improves completion of the road rehabilitation projects.

Unique Contribution to Theory, Practice and Policy: United Nations Joint Programme on Local Governance should effectively engage key stakeholders during the scoping stage of any future road rehabilitation projects. The organization should also ensure that all key stakeholders including employees are consulted and involved in drafting any project plan. This is expected to enhance buy-in and reduce resistance during the changes that will take place in the implementation phase. The United Nations Joint Programme on Local Governance should ensure that control procedures are put into place to certify that all activities are monitored as execution progresses. The theories used, that is Stakeholder theory and the Theory of Reasoned Actions were found applicable to this study and can be used by other scholars in studies related to the research topic.

Downloads

Download data is not yet available.

References

Argawal, F. and Singh, M. (2013). Some Strategies for Sustainable Maintenance of Rural Roads in India. International Journal of Advanced Engineering Technology: Vol. 1; (3)

Asif, T. (2012). The Promise of Rural Roads: Review of the role of low-volume roads connectivity, poverty reduction, crisis management and livability.

Austin, T. (2012). Modern Road Construction; A practical treatise on the engineering problems of road building, with carefully Compiled Specifications for Modern Highways and City Streets and Boulevards, University of Nairobi, University press.

Ayatah, A. K. (2012). Examining Stakeholder Management Challenges and their impact on Project Management in the case of Advocacy and empowerment NGOs in the upper East region of Ghana. Ghana: Kwame Nkrumah University of Science and Technology

Bourne, L. (2008). Stakeholder relationship management maturity. Management Decision 43(5):649-660.

Bundi, M. (2013). Challenges in the management of road construction resources within Kenya Rural Roads Authority. Journal of Operation Management, 25, 732-749.

Carter, M. (2012). Factors Leading Towards Realization of Quality Infrastructure in Sub-saharan Africa. Review of Economics and Statistics, vol. 49, 2012, pp 92-107

Chan, K. and Kumaraswamy, N. (2012). An evaluation of construction time performance in building industry. Building and Environment, 31(6), 569-578.

Faiz, G. (2012). The Promise of Rural Roads; Review of the Role of Low-Volume Roads in Rural Connectivity, Poverty Reduction, Crisis Management, and Livability. Transportation Research Board, Washington D.C.

Friedman, A.L. and Miles, S. (2006). "Stakeholders: Theory and Practice", Oxford University Press

Graw-hill, G. (2014). Project management: the managerial process (4th ed.) McGraw-Hill Irwin.

Hassan, A. I. (2012). Influence of stakeholder role on performance of constituencies development fund projects a case of Isiolo North Constituency Kenya. University of Nairobi repository.

Ikiara et al., (2013). Kenya's trade in services: should the country fully liberalize?"Ÿ Paper presented to the AERC-KIPPRA Workshop on World Trade Organization (WTO) Agreements, held 11-12 September 2000, Nairobi.

Ipingbemi, N. (2012). Exploring Labour-Based Approach for Rural Road Maintenance in Nigeria. J. Soc. Sci., 17(2): 103-111

Kastner, R. (2010). Why Projects Succeed: Stakeholder Management Challenges Justification for Planning'. Planning Theory, 1:2 pp ,I63- 87.

Kuprenas, H. (2013). Project Organizational Top Management actions to improve design phase cost performance. Journal of Organizational Top Management in Engineering, Vol. 19, (1), 25- 32.

Leesard, R., (2011) Strategic Management of Large Engineering Projects: Shaping Journal of knowledge management, 4(3), 195-203.

Magidu T. (2010). Issues of local level management, Rural Transport Knowledge Base. Rural Travel and Transport Programme

Malunga, M. and Banda V. (2016). Potential and limitations of stakeholders' participation in community- based projects. International Development Planning Review, 26(1), 61-82.

Mbaabu, J. (2012). Mastering project management: Applying advanced concepts to systems thinking, control & evaluation, resource allocation. McGraw Hill Professional.

Menoka, R. (2014) Stakeholder Engagement and Sustainability-related Project Performance in Construction. Journal of Project Management .Vol.3.

Meredith P, (2013). Project Management: a managerial approach. New York: Wiley and sons.

Mohapatra, B. and Chandrasekhar, E. (2012). Rural Roads and Poor Area Development in Vietnam. World Bank Policy Research Working Paper, Washington D. C.

Ngai, N., Drew, L. & Skitmore, W. (2013). Factors influencing project success. International Project Organizational Top Management Handbook ed. D.I. Cleland and W.R.King 2nd edition 902-919, New York.

Njogu, E.M. (2016). Influence of stakeholders' involvement on project performance: A Case of Nema Automobile Emmission Control Project in Nairobi County, Kenya.

Nyamwaro, C. (2012). Kenya Institute of for Public Policy and Research Analysis, Analysis studies of Road Infrastructure Policies in Kenya: Historical trends and current challenges. Bishops Garden Towers, Kenya, Nairobi.

Nyonje R. O., Ndunge K. D. and Mulwa A. S. (2012), Monitoring and Evaluation of Projects and Programmes, A handbook for students and Practitioners, Aura Books

O'Halloran, M. (2014). The Awareness of Stakeholder Management amongst Project Managers in the Construction Industry in Ireland.

Ogunlana S. O. (2017). Factors affecting cost and time performance on highway construction projects: Evidence from Thailand

Onchoke, N.A.(2016). Stakeholders' Capacity Building and Participation in Monitoring and Evaluation of Urban Water Supply and Health Projects in Kenya: Case of Kisii Town, Kisii County. Journal of Geography and Natural Disaster, 6(2), 13-32.

Ondieki, W. M. (2011). Factors influencing stakeholders' participation in monitoring and evaluation of Local Authority transfer fund projects in Kisii municipality, Kenya.

Otim, G. & Alinaitwe, H. M. (2011). Factors affecting the performance of pavement road construction projects in Uganda.

Raissudin et al, (2013). Automated project performance control of road construction projects. Automation in Construction, Vol. 14, 467- 476.

RICS Research,(2016). The Practice of Stakeholder Engagement in Infrastructure Projects: A comparative study of two major projects in Australia and the UK.

Sama-Lang, I., & Zesung, A. (2016). The stakeholder theory of corporate control and the place of ethics in OHADA: The case of Cameroon. African Journal of Business Ethics, 10(1), 97-111.

Schonher, M. and Mbugua, L.H (2013). Road Network Development Master Plan Study of the Republic of Kenya, vol11, Annex 11; Technical Assessment of the existing road network. Nairobi, government press.

Waithera, S.L. (2015). Influence of Project Monitoring and Evaluation on Performance of Youth Funded Agribusiness Projects in Bahati Sub-County, Nakuru, Kenya. International Journal of Economics, Commerce and Management, 3(11), 121-132.

Walker, A. (2015). Project Management in Construction. United Kingdom: John Wiley and Sons.

Winch, G. (2010).Managing construction projects: An information processing approach. Chichester: Blackwell Pub.

World Bank, (2014). Maintaining and Rehabilitating the Road Network for Growth, Washington: World Bank.

Yang, R.J., Wang Y. and Jin, X.H., (2014). Stakeholders' Attributes, Behaviors, and Decision-Making Strategies in Construction Projects: Importance and Correlations in Practice. Project Management Journal, 45:3 74-90.

Zenko, Z. (2013). General Systems Theory Completed Up by Dialectical Systems Theory. Systems Research & Behavioral Science, 30(6), 637-645.

Downloads

Published

2022-10-07

How to Cite

Karuri , S., & Karanja, A. (2022). Influence of Project Initiation on Completion of United Nations Joint Programme on Local Governance Road Rehabilitation Projects. International Journal of Entrepreneurship and Project Management, 7(1), 47–63. https://doi.org/10.47604/ijepm.1661

Issue

Section

Articles