DETERMINANTS OF SUCCESSFUL COMPLETION OF HOUSING PROJECTS AT NATIONAL HOUSING CORPORATION IN KENYA.
Keywords:
Project management, project planning, stakeholder, project success, monitoring, evaluation, resources.Abstract
Purpose: To establish the determinants of successful completion of housing projects at National Housing Corporation in Kenya.
Methodology: This study employed descriptive research design. The design was suitable for the study because it described the situation regarding successful completion of housing projects at NHC. The target population was staff members in project management department at the National Housing. The unit of observation was 115 staff members. The research used both primary and secondary data. A five point Likert scale poll was utilized to get essential information on the independent variables of the research, that is; planning, monitoring and evaluation, shareholders involvement and resource accessibility. Primary data was gathered through the administration of questionnaires to respondents. Questionnaires were used because of their ability to reach big audience from different sources. Multiple linear regression was done to establish the influence of independent variable on dependent variable.
Results: The study established significant and positive relationship between the independent variables and dependent variables. Project planning of housing projects had a significant and positive influence (β = 0.079 and p = 0.03) on the project success. Monitoring and evaluation had a positive and significant ((β = 0.122 and p = 0.02) influence on completion of housing projects. Additionally, it was revealed that stakeholder involvement had a positive and significant (β = 0.164 and p = 0.045) influence on completion of housing projects. Further, the study revealed resource availability had a positive and significant (β = 0.09 and p = 0.038) influence on completion of housing projects.
Unique Contribution to theory, practice and policy: The study prescribes NHC to include its stakeholders in any project endeavour for an effective finish of the housing projects. The study also recommended that projects managers need to be more detailed in their planning to eliminate projects bottlenecks.
Downloads
References
Al Nasseri, H. A., Widen, K., &Aulin, R. (2016). A taxonomy of planning and scheduling methods to support their more efficient use in construction project management. Journal of Engineering, Design and Technology, 14(3), 580-601.
Alias, Z., Zawawi, E. M. A., Yusof, K., &Aris, N. M. (2014). Determining critical success factors of project management practice: A conceptual framework. Procedia-Social and Behavioral Sciences, 153, 61-69.
Banathy, B. H. (2013). Designing social systems in a changing world. Springer Science & Business Media.
Chirkunova, E. K., Kireeva, E. E., Kornilova, A. D., &Pschenichnikova, J. S. (2016). Research of instruments for financing of innovation and investment construction projects. Procedia Engineering, 153, 112-117.
Enshassi, A., Mohamed, S., &Abushaban, S. (2014). Factors affecting the performance of construction projects in the Gaza strip. Journal of Civil engineering and Management, 15(3), 269-280.
Fadare, Z. (2013). Social housing initiative review. Kuala Lumpur, Malaysia. Journal of Design and Built Environment, Vol. 7, p p 43-57.
Fewings, P. (2013). Construction project management: an integrated approach. Routledge.
GoK, (2015). Causes of delay and cost overruns in Kenyan construction projects. International Journal of Project Management 1 (4): pp 254-60.
GudienÄ—, N., Banaitis, A., Podvezko, V., &BanaitienÄ—, N. (2014). Identification and evaluation of the critical success factors for construction projects in Lithuania: AHP approach. Journal of Civil Engineering and Management, 20(3), 350-359.
Hatch, Z. (2013). Construction delays in a fast growing economy: Comparing Thailand with other economies. International Journal of Project Management, 14(1), 37-45.
Planning'. Planning Theory, 1:2 ppI63 87.
Kermanshachi, S. (2016). Decision Making and Uncertainty Analysis in Success of Construction Projects (Doctoral dissertation).
Kerzner, H. (2013). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to measuring and monitoring project performance. John Wiley & Sons.
Kerzner, H., &Kerzner, H. R. (2017). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.
Langat, D. K. (2015). Factors influencing completion of construction projects in public secondary schools in Bomet east sub-county, Bomet county, Kenya (Doctoral dissertation, Doctoral Dissertation, University of Nairobi).
Li, L., Li, Z., Wu, G., & Li, X. (2018). Critical Success Factors for Project Planning and Control in Prefabrication Housing Production: A China Study. Sustainability, 10(3), 836.
Li, V. (2013). A methodology to assess the competitiveness of real estate developers in China (Doctoral dissertation, Queensland University of Technology).
Liu, J., Zhao, X., & Yan, P. (2016). Risk paths in international construction projects: Case study from Chinese contractors. Journal of Construction Engineering and Management, 142(6), 05016002.
Mahamid, I. (2016). Factors contributing to poor performance in construction projects: studies of Saudi Arabia. Australian Journal of Multi-Disciplinary Engineering, 12(1), 27-38.
Munyoki, K. (2014). Factors influencing completion of construction projects; a case of construction projects in Nairobi, Kenya (Doctoral dissertation, Master's Thesis, University of Nairobi).
Mwathi, K. (2013). Service quality of building maintenance contractors in Zambia: a pilot study. International Journal of Construction Management, 10(3), 63-81.
Ngure, E. W. (2013). Determinants influencing performance of agricultural projects: A case of NALEP projects in Ruiru District, Kiambu County, Kenya (Doctoral dissertation).
Oyeyipo, O., Odusami, K. T., Ojelabi, R. A., &Afolabi, A. O. (2016). Factors Affecting Contractors' Bidding Decisions for Construction Projects in Nigeria. Journal of Construction in Developing Countries, 21(2), 21-35.
Taye, M. (2016). Assessment of Time and Cost Overruns in Construction Projects (Case Study at Defense Construction Enterprise) (Doctoral dissertation, St. Mary's University).
Volker, M. (2012). Evaluation of stakeholder influence in the implementation of construction projects. International journal of project management, 23(4), 321-328.