Assessment of Level of Service for Roads under Performance Based Road Maintenance in Kenya
DOI:
https://doi.org/10.47604/ijts.1944Keywords:
Level of Service, PBRM, Performance Indicators, Ratings, Payment ReductionsAbstract
Purpose: This paper seeks to assess Level of Service (LOS) of roads under performance-based road maintenance (PBRM) in Kenya. This was done through a comparison of actual ratings with performance targets defined by the agencies for each asset item within a sample unit. The comparison was used to determine if each asset item had been preserved at minimum acceptable Level of Service (LOS) with objective of establishing if there are any benefits accrued from adopting the PBRM method.
Methodology: Seven roads were identified in the study area and were divided into 14 sample units, each sample unit containing different asset items to be assessed. Data from the field was collected and recorded using field measurement tools for linear measurements. Dynamic Response Intelligent equipment (DRIMS) was used for measurement of International Roughness Index (IRI). Raw data was converted into performance information using guidelines from Quality Assurance in Highway Maintenance Programs and measurement of conformance conducted using Schedule Performance Index.
Findings: The performance obtained indicated that the goal objective for each road was not achieved with an overall performance deviating from the target performance by 25.05%. However, there was 10% compliance at the asset group level and 35% compliance at asset item level. Noncompliance at road section level, 10% compliance at asset group level and 35% compliance at asset item level signifies inadequacies in PBRM practice in Kenya. This informs need for improvement by road agencies and contractors for optimum benefits from PBRM. There is need for contractor capacity building and enhanced partnering environment between contractors and management engineering consultants to provide technical assistance for improved contractor compliance in PBRM practice.
Unique Contribution to Theory, Practice and Policy: The Concept of Performance based road maintenance (PBRM) is meant to solve problems arising from traditional contracting methods. As demonstrated in this study, effective application of PBRM principles results in cost savings in managing and maintaining roads, expenditure certainty, reduced inhouse workforce, greater road user satisfaction and improved conditions of contracted road assets. The requirement for contractors to provide a product of predefined quality is a definite means of ensuring that the road asset is performing over extended time. It is recommended that PBRM is adopted widely in road asset management to achieve an effective and efficient road network.
Downloads
References
Berg, C, N., Deichmanmm, U, K., Liu, Y., Selod, H. (2015). Transport Policies and Development. Policy Research Working Paper, No. WPS 7366.
Bushey, R., & Kwak, Y.H., (2000). "Construction management at risk: an Innovative project delivery method at stormwater treatment area in the Everglades, Florida", Construction Congress VI: Building Together for a Better Tomorrow in an Increasingly Complex World Proceedings of Construction Congress VI, ASCE, Orlando, FL.
Carpenter, B. et al, (2003). Performance-Based Contracting for the Highway Construction Industry, an Evaluation of the Use of Innovative Contracting and Performance Specification in Highway Construction. Washington, DC, Koch Industries.
Chebon C. C., (2013). Development of Road Maintenance Management System for Unpaved roads in Kenya. Jomo Kenyatta University, Nairobi.
ENRA (Estonian National Road Administration). (2004). Annual Report 2003. Tallinn.
FHWA (United States Federal Highway Administration). (2005). "Highway Maintenance Contracting 2004. World State of Practices." Report of the National Highway Maintenance Contract Seminar, April 2004. Orlando, Florida, USA.
ISO 9001:2015., International Organization for Standardization, Geneva.
Japan International Cooperation Agency (JiCA), (2016). Performance Based Road Maintenance Contract Guideline (Edition 1.1). Limuru, Kenya: Franciscan Kolbe Press
Kenny, C., (2007). "Construction, corruption, and developing countries", Working Paper No. 4271, World Bank Policy Research, The World Bank, Washington, DC.
Kenya Rural Roads Authority (KeRRA), (2015). Approved Low Volume Seal Roads Brochure. Nairobi. Retrieved from http//www.kerra.go.ke.
Lande, K., (1999). Privatized Highway Asset Management - Management of Subcontract Maintenance. Retrieved from http://www.zietlow.com/docs/vms1_00a.htm
Liautaud, G. 2004. "Maintaining Roads: Experience with Output-based Contracts in Argentina." Washington, D.C.: The World Bank. http://rru.worldbank.org/Documents/Other/09ch4.pdf
Ministry of Transport, Roads and Public Works, MTRPW. (2014). The Roads Sub-Sector Policy, Nairobi.
Ozbek, M. E., & de la Garza, J. M., (2007). Development of Performance Warrantees for Performance Based Road Maintenance Contracts in Alternative Project Delivery, Procurement and Contracting Methods for Highways (K.R. Molenaar & G. Yakowenko, eds). Reston, VA.
Pinero, C. J., (2003). A Framework for Monitoring Performance-Based Road Maintenance. Virgina University, Virginia.
Reilly, J., (2009). Alternative Contracting and Delivery Methods. Retrieved from www.ctta.org/FileUpload/ita/2009/papers/O-01/O-01-09.pdf
Robinson, M.D. et al. (2006), "DC streets performance-based asset preservation experiment: current quantitative results and suggestions for future contracts", Transportation Research Board 85th Annual Meeting, Transportation Research Board, Washington, DC.
Shrestha, K. K., Shrestha, P. P., Kandie, K. T., (2014). A Road Maintenance Management Tool for Rural Roads in Kenya. Journal for Construction Research Congress. ASCE. Montreal.
Stankevich, N., Qureshi, N., and Queiroz, C., (2005). Performance-Based Contracting for Preservation and Improvement of Road Assets. The World Bank. Transport Note No. TN-27. Washington DC.
Stivers, M. L., Smith, K. L., Hoerner, T. E., and Romine, A. R. (1997) "Maintenance Quality Assurance Program: Implementation Manual" NCHRP Final Manual. Washington DC.
Virginia Department of Transport (VDOT). (2000). Report on VDOT's comprehensive agreement for interstate asset management services: VMS operations for 1999/2000. Maintenance Division. VA.
World Bank, (2009). Resource Guide: Performance-Based Contracting for Preservation and Improvement of Road Assets. Retrieved from http://wwwesd.worldbank.org/pbc_resource_guide/index.html
World Bank, (2014). Review of Performance Based Contracting in the Road Sector -Phase 1. World Bank Transport Note. No. TP-42A. Retrieved from https://openknowledge.worldbank.org/bitstream/handle/10986/18648/878260NWP0TP4200Box377314B00PUBLIC0.pdf?sequence=1
Zietlow, G. 2004. "Implementing Performance-based Road Management and Maintenance Contracts in Developing Countries - An Instrument of German Technical Cooperation." November 2004. Eschborn, Germany. http://www.zietlow.com/docs/PBMMC-GTZ.pdf
Zietlow, G.J. (2005), "Cutting costs and improving quality through performance-based road management and maintenance contracts-the Latin American and OECD experiences", Senior Road Executives Program. Restructuring Road Management, German Development Cooperation, Birmingham.
Zietlow, G. J., (2015). Road Asset Management and Performance Based Contracts. Presentation. Manila: ADB
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2023 Dominic Kundu, Zachary Gariy, Timothy Nyomboi
This work is licensed under a Creative Commons Attribution 4.0 International License.
Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution (CC-BY) 4.0 License that allows others to share the work with an acknowledgment of the work's authorship and initial publication in this journal.