Influence of Stakeholders' Management on Public Project Success: Evidence from Kenya
DOI:
https://doi.org/10.47604/ijepm.2059Keywords:
Stakeholders Management, Project Success, Stakeholders, Analysis, Involvement and Expectation ManagementAbstract
Purpose: The purpose of this study was to examine the influence of stakeholders' management on public projects success in Kenya:
Methodology: This study adopted a descriptive cross-sectional survey design. The target population was 500 staff working for the Kenya government. The study population included public work engineers, works clerks, public project managers, contractors, supervisors and community elder respondents. The research study embraced stratified random sampling method and a sample size of 150 respondents was obtained using the Yamane (1967) formula. The study further used structured questionnaires which consisted of both open-ended and closed-ended questions to collect data from the sampled population. The collected data was cleaned for clarity clearness. Coding was done on the basis of the place of the participants. The data was analyzed using excel. Data was presented using frequency tables
Finding: The findings revealed that stakeholders' analysis has a positive influence on public project success. Majority of the respondents agreed that stakeholders and their roles have been successfully identified. The study concludes that stakeholders' participation had a positive impact on project success. In addition, the study suggests that proper stakeholder expectation management enhances project success.
Unique Contribution to Theory, Practice and Policy: The study affirmed applications of stakeholder's theory since internal and external stakeholders power determines the success of public projects. For Practice, Public Project implementors should enhance stakeholder involvement in project decision-making. There is need for improvement in participatory planning and budgeting to enhance decision-making processes. In addition, the government should refine stakeholder management process by designing policy for stakeholder engagement. The policy, should emphasize the need to address concerns related to service timeliness, quality, and budget adherence, as well as enhancing feedback mechanisms and communication channels. Proper timeliness and quality of service delivery need to be enhanced. The government should establish mechanisms for participatory planning and budgeting, providing stakeholders with resources for active participation, addressing service timeliness and quality concerns.
Downloads
References
Freeman, R. E. E., & McVea, J. (2005). A Stakeholder Approach to Strategic Management. SSRN Electronic Journal, January. https://doi.org/10.2139/ssrn.263511
Githinji, C. N., Ogolla, P., & Kitheka, S. (2020). Influence of stakeholder's involvement on project performance. A case study of Kenya Ferry Services. The Strategic Journal of Business & Change Management, 7(3), 738-756.
Mageto, G. J., Kitheka, S., & Ogolla, P. (2021). International Journal of Advanced Research and Review www.ijarr.in Effect Of Project Stakeholders Management On Performance Of Road Construction Projects In Mombasa County, Kenya. Ijarr, 6(5), 10-24. www.ijarr.in
Mok, M. K. Y., & Shen, G. Q. (2016). A network-theory Based Model for Stakeholder Analysis in Major Construction Projects. Procedia Engineering, 164(June), 292-298. https://doi.org/10.1016/j.proeng.2016.11.622
Muhiai, M. N., Wanjala, Y. M., Mike, P., & Iravo, A. (2018). Factors Influencing Stakeholders Management in Effective Implementation of Water Projects in Kiambu County , Kenya. 5(2), 155-160.
Ndiang, D., Wambui, ui, Ombui, K., & Kagiri, A. (2014). Factors Affecting Completion of Road Construction Projects in Nairobi City County: Case Study of Kenya Urban Roads Authority (KURA). International Journal of Scientific and Research Publications, 5(11), 525. www.ijsrp.org
Ngilambi and McCubbin. (2017). Towards effective implementation of community based water safety plans: stakeholders engagement process in Afghanistan. 1-8.
Ngwai, F. M., Simba, F., & Oyoo, J. J. (2019). Influence of Project Management Practices on Construction Cost Control of Projects in Mombasa County. 314-330. www.strategicjournals.com
Nyandika, O. O., & Ngugi, K. (2014). Influence of Stakeholders' Participation on Performance of Road Projects At Kenya National Highways Authority. European Journal of Business Management, 1(11), 384-404. http://www.ejobm.org
Oke, A. E., & Aigbavboa, C. (2016). Performance of Construction Projects in South Africa : Perceptions of Consultants and Contractors. In Proceedings of the DII-2016 Conference on Infrastructure Development and Investment Strategies for Africa: Achieving Solutions for Renewable Energy and Sustainable Development (Issue February 2017).
Peng, R., Chang, L., & Liwen, Z. (2017). China's involvement in coal-fired power projects along the Belt and Road. Global Environmental Institute, May. http://www.geichina.org/_upload/file/report/China's_Involvement_in_Coal-fired_Power_Projects_OBOR_EN.pdf
Shokri-Ghasabeh, M., & Kavousi-Chabok, K. (2009). Generic project success and project management success criteria and factors: Literature review and survey. WSEAS Transactions on Business and Economics, 6(8), 456-468.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2023 Kipyego Aloket Samwel, Marube Dennis Nyamiaka , Lucy Ndung'u Wamaitha, Simon Muriu Waichigo
This work is licensed under a Creative Commons Attribution 4.0 International License.
Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution (CC-BY) 4.0 License that allows others to share the work with an acknowledgment of the work's authorship and initial publication in this journal.